πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Gosfield Airfield

Gosfield Airfield, Land At Southey Green Sible, Hedingham, Essex, Essex, CO9 3

Gosfield Airfield is a 12.6 MW solar farm project in Eastern. The applicant or operator on record is Push Energy. It is recorded as operational since February 2015. The determining authority is Braintree, reference 13/01463/FUL.…

Operational Β· Since 2015
Project stageOperating
  1. PlanningDec 2013 (completed)
  2. ConsentedApr 2014 (completed)
  3. ConstructionOct 2014 (completed)
  4. OperatingFeb 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-03-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

12.600 MW
Registered Capacity
2015
Commissioned

πŸ“‹ Project Overview

Gosfield Airfield is a 12.6 MW solar farm project in Eastern. The applicant or operator on record is Push Energy. It is recorded as operational since February 2015. The determining authority is Braintree, reference 13/01463/FUL.

Site Schematic

SUBSTATION ? ha Β· 12.6 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)12.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPush Energy
Owner / operatorPush Energy
Year consented2014
Construction started2014
Commissioned / target2015
LocationGosfield Airfield, Land At Southey Green Sible, Hedingham, Essex, Essex, CO9 3
RegionEastern
Coordinates51.9557977Β°N, 0.5796875Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2013-12-23
2014-04-17
2014-10-01
2015-02-01