πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Gortahurk Road

11 Gortahurk Road, Derrylin, Tonymore, Enniskillen, Co. Fermanagh, BT92 9DD

Gortahurk Road is a 1.5 MW bioenergy / waste project in Northern Ireland. The applicant or operator on record is Connective Energy Holdings. It is recorded as operational since March 2018. The determining authority is Fermanagh and Omagh, reference LA10/2016/1232/F.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningDec 2016 (completed)
  2. ConsentedMar 2017 (completed)
  3. ConstructionMar 2017 (completed)
  4. OperatingMar 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-09-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.500 MW
Registered Capacity
2018
Commissioned

πŸ“‹ Project Overview

Gortahurk Road is a 1.5 MW bioenergy / waste project in Northern Ireland. The applicant or operator on record is Connective Energy Holdings. It is recorded as operational since March 2018. The determining authority is Fermanagh and Omagh, reference LA10/2016/1232/F.

πŸ”§ Technical Specifications

Capacity (MW)1.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperConnective Energy Holdings
Owner / operatorConnective Energy Holdings
Year consented2017
Construction started2017
Commissioned / target2018
Location11 Gortahurk Road, Derrylin, Tonymore, Enniskillen, Co. Fermanagh, BT92 9DD
RegionNorthern Ireland
Coordinates54.2194841Β°N, 7.5402286Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2016-12-01
2017-03-16
2017-03-30
2018-03-30