πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Glenshimmeroch Wind Farm

Land At Glenshimmeroch Hill, St. John's Town of Dalry, Dalry, Castle Douglas, Dumfries and Galloway, DG7 3XL

Glenshimmeroch Wind Farm is a 36 MW onshore wind project in Scotland. The applicant or operator on record is EnergieKontor UK. Planning permission has been granted as of September 2019 and it is awaiting construction. The determining authority is Dumfries and Galloway, reference …

Consented / Approved
Project stageConsented
  1. PlanningJul 2018 (completed)
  2. ConsentedSep 2019 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Appeal Granted.

Official register: July 2026

Recorded status: Appeal Granted. Source record updated 2024-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

36.000 MW
Registered Capacity

πŸ“‹ Project Overview

Glenshimmeroch Wind Farm is a 36 MW onshore wind project in Scotland. The applicant or operator on record is EnergieKontor UK. Planning permission has been granted as of September 2019 and it is awaiting construction. The determining authority is Dumfries and Galloway, reference 18/0992/FUL.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)36.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEnergieKontor UK
Owner / operatorEnergieKontor UK
Year consented2019
LocationLand At Glenshimmeroch Hill, St. John's Town of Dalry, Dalry, Castle Douglas, Dumfries and Galloway, DG7 3XL
RegionScotland
Coordinates55.165713Β°N, 4.1047705Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)3.6
No. of Turbines10
Height of Turbines (m)200

πŸ“… Project Timeline

2018-07-02
2019-09-04