Glenkerie Wind Farm Extension is a 15 MW onshore wind project in Scotland. The applicant or operator on record is Muirhall Energy (formerly Infinis). The planning permission has expired. The determining authority is Scottish Borders, reference 13/00552/FUL.…

Expired
Project stageConsent lapsed
  1. PlanningMay 2013 (completed)
  2. ConsentedJul 2015 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2020-09-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

15.000 MW
Registered Capacity

πŸ“‹ Project Overview

Glenkerie Wind Farm Extension is a 15 MW onshore wind project in Scotland. The applicant or operator on record is Muirhall Energy (formerly Infinis). The planning permission has expired. The determining authority is Scottish Borders, reference 13/00552/FUL.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)15.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperMuirhall Energy (formerly Infinis)
Owner / operatorMuirhall Energy (formerly Infinis)
Year consented2015
LocationKingledores Farm, Broughton, Biggar, Strathclyde, Borders, ML12 6QL
RegionScotland
Coordinates55.5385233Β°N, 3.4204951Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.5
No. of Turbines6

πŸ“… Project Timeline

2013-05-14
2015-07-29