Land Rear Of The Royal Toby Ho, Manchester Road, Rochdale, Greater Manchester, OL11 3HF
Gipsy Lane is a 20 MW battery storage project in North West. The applicant or operator on record is Arlington Energy. It is recorded as under construction since July 2021. The determining authority is Rochdale, reference 19/01147/FUL.β¦
Under Construction
Project stageUnder construction
PlanningNov 2019 (completed)
ConsentedMar 2020 (completed)
ConstructionJul 2021 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2021-07-01.
Registered planning capacity; not measured generation.
Gipsy Lane is a 20 MW battery storage project in North West. The applicant or operator on record is Arlington Energy. It is recorded as under construction since July 2021. The determining authority is Rochdale, reference 19/01147/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
20.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Arlington Energy
Owner / operator
Arlington Energy
Year consented
2020
Construction started
2021