Gigha Wind Farm Battery Project

Gigha, Argyll and Bute, PA41 7AB

Gigha Wind Farm Battery Project is a 0.1 MW battery storage project in Scotland. The applicant or operator on record is Gigha Island community (Multiple Owners). The scheme is currently in the planning system. The determining authority is Argyll and Bute.…

Decommissioned Β· Target 2016
Project stageClosed
  1. Planning (completed)
  2. Consented (completed)
  3. ConstructionNov 2015 (completed)
  4. OperatingDec 2016 (completed)
  5. Closed (current stage)

Status in the official register: Decommissioned.

Official register: July 2026

Recorded status: Decommissioned. Source record updated 2017-07-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.100 MW
Power Capacity
2016
Target Date

πŸ“‹ Project Overview

Gigha Wind Farm Battery Project is a 0.1 MW battery storage project in Scotland. The applicant or operator on record is Gigha Island community (Multiple Owners). The scheme is currently in the planning system. The determining authority is Argyll and Bute.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.100 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGigha Island community (Multiple Owners)
Owner / operatorGigha Island community (Multiple Owners)
Construction started2015
Commissioned / target2016
LocationGigha, Argyll and Bute, PA41 7AB
RegionScotland
Coordinates55.6845934Β°N, 5.7490962Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2015-11-15
2016-12-15