Carlton Grange, Thacker Bank, Great Carlton, Gayton Le Marsh, Louth, Lincolnshire (3.3km to the northeast of Great Carlton and 2.4km south of Saltfleetby), Lincolnshire, LN11 7TXL
Gayton Le Marsh Wind Farm is a 16.4 MW onshore wind project in East Midlands. The applicant or operator on record is Energiekontor UK. It is recorded as operational since February 2016. The determining authority is East Lindsey, reference N/063/01392/11.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningAug 2011 (completed)
ConsentedApr 2013 (completed)
ConstructionFeb 2015 (completed)
OperatingFeb 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-03-04.
Registered planning capacity; not measured generation.
Gayton Le Marsh Wind Farm is a 16.4 MW onshore wind project in East Midlands. The applicant or operator on record is Energiekontor UK. It is recorded as operational since February 2016. The determining authority is East Lindsey, reference N/063/01392/11.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
16.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Energiekontor UK
Owner / operator
Energiekontor UK
Year consented
2013
Construction started
2015
Commissioned / target
2016
Location
Carlton Grange, Thacker Bank, Great Carlton, Gayton Le Marsh, Louth, Lincolnshire (3.3km to the northeast of Great Carlton and 2.4km south of Saltfleetby), Lincolnshire, LN11 7TXL