Gayton Le Marsh Wind Farm

Carlton Grange, Thacker Bank, Great Carlton, Gayton Le Marsh, Louth, Lincolnshire (3.3km to the northeast of Great Carlton and 2.4km south of Saltfleetby), Lincolnshire, LN11 7TXL

Gayton Le Marsh Wind Farm is a 16.4 MW onshore wind project in East Midlands. The applicant or operator on record is Energiekontor UK. It is recorded as operational since February 2016. The determining authority is East Lindsey, reference N/063/01392/11.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningAug 2011 (completed)
  2. ConsentedApr 2013 (completed)
  3. ConstructionFeb 2015 (completed)
  4. OperatingFeb 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-03-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

16.400 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Gayton Le Marsh Wind Farm is a 16.4 MW onshore wind project in East Midlands. The applicant or operator on record is Energiekontor UK. It is recorded as operational since February 2016. The determining authority is East Lindsey, reference N/063/01392/11.

Site Schematic

EAST MIDLANDS Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)16.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEnergiekontor UK
Owner / operatorEnergiekontor UK
Year consented2013
Construction started2015
Commissioned / target2016
LocationCarlton Grange, Thacker Bank, Great Carlton, Gayton Le Marsh, Louth, Lincolnshire (3.3km to the northeast of Great Carlton and 2.4km south of Saltfleetby), Lincolnshire, LN11 7TXL
RegionEast Midlands
Coordinates53.3626376Β°N, 0.1660001Β°E

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.05
No. of Turbines8

πŸ“… Project Timeline

2011-08-15
2013-04-05
2015-02-17
2016-02-26