Land At Gawcott Fields Farm Gawcott Road Buckingham Buckinghamshire MK18 1TN, Buckinghamshire
Gawcott Fields Farm is a 9.2 MW solar farm project in South East. The applicant or operator on record is Harper Solar Ltd. It is recorded as operational since December 2015. The determining authority is Buckinghamshire, reference 14/02293/APP.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJul 2014 (completed)
ConsentedOct 2014 (completed)
ConstructionNov 2015 (completed)
OperatingDec 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-04-25.
Registered planning capacity; not measured generation.
Gawcott Fields Farm is a 9.2 MW solar farm project in South East. The applicant or operator on record is Harper Solar Ltd. It is recorded as operational since December 2015. The determining authority is Buckinghamshire, reference 14/02293/APP.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
9.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Harper Solar Ltd
Owner / operator
Harper Solar Ltd
Year consented
2014
Construction started
2015
Commissioned / target
2015
Location
Land At Gawcott Fields Farm Gawcott Road Buckingham Buckinghamshire MK18 1TN, Buckinghamshire