Conventional Hydro

Gaineamhach Hydro Scheme Powerhouse

Land 3160M SW Of, Kerry Falls House, Gairloch, Highland, IV21 2AH

Gaineamhach Hydro Scheme Powerhouse is a 2 MW conventional hydro project in Scotland. The applicant or operator on record is Hydroplan/Three Lochs Hydro. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining authority is Highland…

Consented / Approved
Project stageConsented
  1. PlanningNov 2018 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-03-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity

πŸ“‹ Project Overview

Gaineamhach Hydro Scheme Powerhouse is a 2 MW conventional hydro project in Scotland. The applicant or operator on record is Hydroplan/Three Lochs Hydro. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining authority is Highland, reference 18/05132/FUL.

Site Schematic

UPPER RES. LOWER RES. PENSTOCK TAILRACE GEN. GRID HEAD: ?m Β· POWER: 2.000 MW Β· ? turbines

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHydroplan/Three Lochs Hydro
Owner / operatorHydroplan/Three Lochs Hydro
Year consented2023
LocationLand 3160M SW Of, Kerry Falls House, Gairloch, Highland, IV21 2AH
RegionScotland
Coordinates57.6576057Β°N, 5.6593021Β°W

Additional published register fields

Registered technologySmall Hydro
Are they re-applying (Old REPD Ref) 6195

πŸ“… Project Timeline

2018-11-05
2023-10-23