Funtley Refuse Tip, Titchfield Lane, Wickham, Fareham, Hampshire, PO15 6DY, Hampshire, PO15 6DY

Funtley Refuse Tip is a 10 MW solar farm project in South East. The applicant or operator on record is Cassidy & Ashton Group Ltd. The planning permission has expired. The determining authority is Winchester, reference 13/01247/FUL.…

Expired
Project stageConsent lapsed
  1. PlanningJun 2013 (completed)
  2. ConsentedAug 2013 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2017-09-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.000 MW
Registered Capacity

πŸ“‹ Project Overview

Funtley Refuse Tip is a 10 MW solar farm project in South East. The applicant or operator on record is Cassidy & Ashton Group Ltd. The planning permission has expired. The determining authority is Winchester, reference 13/01247/FUL.

Site Schematic

SUBSTATION ? ha Β· 10 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)10.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCassidy & Ashton Group Ltd
Owner / operatorCassidy & Ashton Group Ltd
Year consented2013
LocationFuntley Refuse Tip, Titchfield Lane, Wickham, Fareham, Hampshire, PO15 6DY, Hampshire, PO15 6DY
RegionSouth East
Coordinates50.8802395Β°N, 1.2205502Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)230400

πŸ“… Project Timeline

2013-06-05
2013-08-28