Frodo Solar Farm, Crimond, Fraserburgh, Aberdeenshire, AB43 8QH

Frodo Solar and Battery Energy Development is a 50 MW battery storage project in Scotland. The applicant or operator on record is Green Energy International. Planning permission has been granted as of May 2023 and it is awaiting construction. The determining authority is Scottish…

Consented / Approved
Project stageConsented
  1. PlanningMar 2022 (completed)
  2. ConsentedMay 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-04-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Frodo Solar and Battery Energy Development is a 50 MW battery storage project in Scotland. The applicant or operator on record is Green Energy International. Planning permission has been granted as of May 2023 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00003345.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGreen Energy International
Owner / operatorGreen Energy International
Year consented2023
LocationFrodo Solar Farm, Crimond, Fraserburgh, Aberdeenshire, AB43 8QH
RegionScotland
Coordinates57.6012284Β°N, 1.9151559Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID10993
Mounting Type for SolarGround

πŸ“… Project Timeline

2022-03-16
2023-05-16