Former Westhampnett Landfill S, Coach Road, Westhampnett, Chichester, West Sussex, PO19 7RT
Former Westhampnett Landfill is a 7.5 MW solar farm project in South East. The applicant or operator on record is West Sussex County Council. It is recorded as operational since October 2018. The determining authority is Chichester, reference WSCC/057/16/WH.β¦
OperationalΒ· Since 2018
Project stageOperating
PlanningSep 2016 (completed)
ConsentedJan 2017 (completed)
ConstructionJul 2017 (completed)
OperatingOct 2018 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-11-08.
Registered planning capacity; not measured generation.
Former Westhampnett Landfill is a 7.5 MW solar farm project in South East. The applicant or operator on record is West Sussex County Council. It is recorded as operational since October 2018. The determining authority is Chichester, reference WSCC/057/16/WH.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
7.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
West Sussex County Council
Owner / operator
West Sussex County Council
Year consented
2017
Construction started
2017
Commissioned / target
2018