Battery Storage

Fideoak Mills

Fideoak Mills, Upcott Road, Bishops Hull, Taunton, Somerset, Somerset, TA4 1AF

Fideoak Mills is a 30 MW battery storage project in South West. The applicant or operator on record is Kiwi Power (formerly Taunton Battery Storage). It is recorded as operational since August 2020. The determining authority is Somerset, reference 05/16/0056.…

Operational Β· Since 2020
Project stageOperating
  1. PlanningDec 2016 (completed)
  2. ConsentedNov 2018 (completed)
  3. ConstructionSep 2019 (completed)
  4. OperatingAug 2020 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-09-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Power Capacity
2020
Commissioned

πŸ“‹ Project Overview

Fideoak Mills is a 30 MW battery storage project in South West. The applicant or operator on record is Kiwi Power (formerly Taunton Battery Storage). It is recorded as operational since August 2020. The determining authority is Somerset, reference 05/16/0056.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKiwi Power (formerly Taunton Battery Storage)
Owner / operatorKiwi Power (formerly Taunton Battery Storage)
Year consented2018
Construction started2019
Commissioned / target2020
LocationFideoak Mills, Upcott Road, Bishops Hull, Taunton, Somerset, Somerset, TA4 1AF
RegionSouth West
Coordinates51.020082Β°N, 3.1547905Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2016-12-02
2018-11-26
2019-09-01
2020-08-01