Mynydd Maesteg and Mynydd Pwllyrhebog, Ogmore and Rhondda Valleys, Mid Glamorgan
Fforch Nest Wind Farm pt2 is a 17.5 MW onshore wind project in Wales. The applicant or operator on record is Pennant Walters. It is recorded as operational since May 2013. The determining authority is Bridgend, reference 06/1842/10.β¦
OperationalΒ· Since 2013
Project stageOperating
PlanningMar 2006 (completed)
ConsentedMay 2011 (completed)
ConstructionOct 2011 (completed)
OperatingMay 2013 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2013-06-05.
Registered planning capacity; not measured generation.
Fforch Nest Wind Farm pt2 is a 17.5 MW onshore wind project in Wales. The applicant or operator on record is Pennant Walters. It is recorded as operational since May 2013. The determining authority is Bridgend, reference 06/1842/10.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
17.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Pennant Walters
Owner / operator
Pennant Walters
Year consented
2011
Construction started
2011
Commissioned / target
2013
Location
Mynydd Maesteg and Mynydd Pwllyrhebog, Ogmore and Rhondda Valleys, Mid Glamorgan