Fernishaw Solar Farm & Battery Energy Storage Facility

east of Fernieshaw Road and west of Muiredge and Jersey Road, Cleland, Lanarkshire, ML1 5NG

Fernishaw Solar Farm & Battery Energy Storage Facility is a 25 MW battery storage project in Scotland. The applicant or operator on record is Elgin Energy (EEB67). Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is S…

Consented / Approved
Project stageConsented
  1. PlanningDec 2023 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-10-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

25.000 MW
Power Capacity

πŸ“‹ Project Overview

Fernishaw Solar Farm & Battery Energy Storage Facility is a 25 MW battery storage project in Scotland. The applicant or operator on record is Elgin Energy (EEB67). Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004871.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)25.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElgin Energy (EEB67)
Owner / operatorElgin Energy (EEB67)
Year consented2025
Locationeast of Fernieshaw Road and west of Muiredge and Jersey Road, Cleland, Lanarkshire, ML1 5NG
RegionScotland
Coordinates55.8119079Β°N, 3.8810751Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID14540

πŸ“… Project Timeline

2023-12-19
2025-07-23