πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Fenmarc Fenland AD Plant (Waste AD)

Wisbech Road, March,, Cambridgeshire, PE15 0BA

Fenmarc Fenland AD Plant (Waste AD) is a 1.5 MW bioenergy / waste project in Eastern. The applicant or operator on record is Local Generation. It is recorded as operational since November 2012. The determining authority is Fenland, reference F/02007/09/CW.…

Operational Β· Since 2012
Project stageOperating
  1. PlanningMay 2009 (completed)
  2. ConsentedJun 2009 (completed)
  3. ConstructionDec 2011 (completed)
  4. OperatingNov 2012 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2013-01-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.500 MW
Registered Capacity
2012
Commissioned

πŸ“‹ Project Overview

Fenmarc Fenland AD Plant (Waste AD) is a 1.5 MW bioenergy / waste project in Eastern. The applicant or operator on record is Local Generation. It is recorded as operational since November 2012. The determining authority is Fenland, reference F/02007/09/CW.

πŸ”§ Technical Specifications

Capacity (MW)1.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLocal Generation
Owner / operatorLocal Generation
Year consented2009
Construction started2011
Commissioned / target2012
LocationWisbech Road, March,, Cambridgeshire, PE15 0BA
RegionEastern
Coordinates52.5680458Β°N, 0.0620735Β°E

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2009-05-27
2009-06-22
2011-12-01