Featherstone House Farm is a 3.2 MW solar farm project in East Midlands. The applicant or operator on record is C A Strawson Ltd. Planning permission has been granted as of April 2016 and it is awaiting construction. The determining authority is Newark and Sherwood, reference 13/…

Consented / Approved
Project stageConsented
  1. PlanningAug 2013 (completed)
  2. ConsentedApr 2016 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2018-10-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.200 MW
Registered Capacity

πŸ“‹ Project Overview

Featherstone House Farm is a 3.2 MW solar farm project in East Midlands. The applicant or operator on record is C A Strawson Ltd. Planning permission has been granted as of April 2016 and it is awaiting construction. The determining authority is Newark and Sherwood, reference 13/00893/FULM.

Site Schematic

SUBSTATION ? ha Β· 3.2 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)3.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperC A Strawson Ltd
Owner / operatorC A Strawson Ltd
Year consented2016
LocationField Reference 2958 Off Mickledale Lane Bilsthorpe Nottinghamshire, Nottinghamshire
RegionEast Midlands
Coordinates53.12903Β°N, 1.0416302Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)57800

πŸ“… Project Timeline

2013-08-02
2016-04-19