Farnborough International Exhibition & Conference Centre, Etps Road, Farnborough, Hampshire, GU14 6TQ
Farnborough International Exhibition Centre, Etps Road - Solar Panels is a 1.15 MW solar farm project in South East. The applicant or operator on record is Farnborough International Limited. It is recorded as under construction since December 2023. The determining authority is Ruβ¦
Under Construction
Project stageUnder construction
PlanningDec 2023 (completed)
ConsentedFeb 2024 (completed)
ConstructionDec 2023 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2024-02-19.
Registered planning capacity; not measured generation.
Farnborough International Exhibition Centre, Etps Road - Solar Panels is a 1.15 MW solar farm project in South East. The applicant or operator on record is Farnborough International Limited. It is recorded as under construction since December 2023. The determining authority is Rushmoor, reference 23/00885/FULPP.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.150 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Farnborough International Limited
Owner / operator
Farnborough International Limited
Year consented
2024
Construction started
2023
Location
Farnborough International Exhibition & Conference Centre, Etps Road, Farnborough, Hampshire, GU14 6TQ