Land opposite Chessington Subs, Fair Oak Lane, Kingston-On-Thames, London, KT9 2NS
Fair Oak Lane is a 49.9 MW battery storage project in London. The applicant or operator on record is Renewable Energy Systems. The planning application was refused. The determining authority is Kingston upon Thames, reference 17/10404.β¦
Refused
Project stageRefused
PlanningOct 2017 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Appeal Refused.
Official register: July 2026
Recorded status: Appeal Refused. Source record updated 2019-06-27.
Registered planning capacity; not measured generation.
Fair Oak Lane is a 49.9 MW battery storage project in London. The applicant or operator on record is Renewable Energy Systems. The planning application was refused. The determining authority is Kingston upon Thames, reference 17/10404.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Renewable Energy Systems
Owner / operator
Renewable Energy Systems
Location
Land opposite Chessington Subs, Fair Oak Lane, Kingston-On-Thames, London, KT9 2NS