πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Factory Extension in Armagh

130 Carrickaness Road, Armagh, Co. Armagh, BT71 7NE

Factory Extension in Armagh is a 3 MW bioenergy / waste project in Northern Ireland. The applicant or operator on record is Greencircle Renewables Ltd. The application has been withdrawn or the scheme abandoned. The determining authority is Armagh City, Banbridge and Craigavon, r…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningJan 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Application Withdrawn.

Official register: July 2026

Recorded status: Planning Application Withdrawn. Source record updated 2022-05-11.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.000 MW
Registered Capacity

πŸ“‹ Project Overview

Factory Extension in Armagh is a 3 MW bioenergy / waste project in Northern Ireland. The applicant or operator on record is Greencircle Renewables Ltd. The application has been withdrawn or the scheme abandoned. The determining authority is Armagh City, Banbridge and Craigavon, reference LA08/2022/0049/F.

πŸ”§ Technical Specifications

Capacity (MW)3.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGreencircle Renewables Ltd
Owner / operatorGreencircle Renewables Ltd
Location130 Carrickaness Road, Armagh, Co. Armagh, BT71 7NE
RegionNorthern Ireland
Coordinates54.3911829Β°N, 6.7583345Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2022-01-14