641metres North of, 28 Altaglushan Road, Galbally, Dungannon, Co. Tyrone
Eshmore Wind Farm Extension is a 2.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. The planning permission has expired. The determining authority is Mid Ulster, reference LA09/2015/0488/F.β¦
Expired
Project stageConsent lapsed
PlanningJul 2015 (completed)
ConsentedJul 2016 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2019-07-19.
Registered planning capacity; not measured generation.
Eshmore Wind Farm Extension is a 2.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. The planning permission has expired. The determining authority is Mid Ulster, reference LA09/2015/0488/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.300 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Energia Renewables
Owner / operator
Energia Renewables
Year consented
2016
Location