Crockanavark, Eshmore and Altaglushan Townlands , Galbally, Dungannon. Co Tyrone, Co. Tyrone
Eshmore is a 6.9 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. It is recorded as operational since December 2016. The determining authority is Mid Ulster, reference M/2006/1802/F.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningOct 2006 (completed)
ConsentedOct 2011 (completed)
ConstructionJan 2016 (completed)
OperatingDec 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-01-04.
Registered planning capacity; not measured generation.
Eshmore is a 6.9 MW onshore wind project in Northern Ireland. The applicant or operator on record is Energia Renewables. It is recorded as operational since December 2016. The determining authority is Mid Ulster, reference M/2006/1802/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Energia Renewables
Owner / operator
Energia Renewables
Year consented
2011
Construction started
2016
Commissioned / target
2016
Location
Crockanavark, Eshmore and Altaglushan Townlands , Galbally, Dungannon. Co Tyrone, Co. Tyrone