Site to the west of, Ernesettle Crescent, Plymouth, Devon, Devon, PL5 2ET
Ernesettle Solar Farm is a 4.1 MW solar farm project in South West. The applicant or operator on record is PEC Renewables. It is recorded as operational since March 2016. The determining authority is Plymouth, reference 15/01377/FUL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningJul 2015 (completed)
ConsentedSep 2015 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-05-27.
Registered planning capacity; not measured generation.
Ernesettle Solar Farm is a 4.1 MW solar farm project in South West. The applicant or operator on record is PEC Renewables. It is recorded as operational since March 2016. The determining authority is Plymouth, reference 15/01377/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
4.100 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
PEC Renewables
Owner / operator
PEC Renewables
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Site to the west of, Ernesettle Crescent, Plymouth, Devon, Devon, PL5 2ET