Willenhall, Wolverhampton, West Midlands, WV13 2NU
EPSRC Willenhall is a 2 MW battery storage project in West Midlands. The applicant or operator on record is University of Sheffield/ Eon/ Uniper. It is recorded as operational since September 2014. The determining authority is Walsall.β¦
OperationalΒ· Since 2014
Project stageOperating
Planning (completed)
Consented (completed)
ConstructionAug 2014 (completed)
OperatingSep 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-10-23.
Registered planning capacity; not measured generation.
EPSRC Willenhall is a 2 MW battery storage project in West Midlands. The applicant or operator on record is University of Sheffield/ Eon/ Uniper. It is recorded as operational since September 2014. The determining authority is Walsall.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
University of Sheffield/ Eon/ Uniper
Owner / operator
University of Sheffield/ Eon/ Uniper
Construction started
2014
Commissioned / target
2014
Location
Willenhall, Wolverhampton, West Midlands, WV13 2NU