πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Electricity Substation, Bellevue Lane - Battery Storage

Adj To Electricity Substation, The A55 At Bellevue Lane, Guilden Sutton, Chester, Cheshire, CH3 7EZ

Electricity Substation, Bellevue Lane - Battery Storage is a 40 MW battery storage project in North West. The applicant or operator on record is Coriolis Energy. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authority is Ches…

Consented / Approved
Project stageConsented
  1. PlanningApr 2024 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-05-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

40.000 MW
Power Capacity

πŸ“‹ Project Overview

Electricity Substation, Bellevue Lane - Battery Storage is a 40 MW battery storage project in North West. The applicant or operator on record is Coriolis Energy. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authority is Cheshire West and Chester, reference 24/00935/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)40.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCoriolis Energy
Owner / operatorCoriolis Energy
Year consented2025
LocationAdj To Electricity Substation, The A55 At Bellevue Lane, Guilden Sutton, Chester, Cheshire, CH3 7EZ
RegionNorth West
Coordinates53.2039131Β°N, 2.8446332Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-04-23
2025-05-07