πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Electricity Sub Station, Strichen - Battery Storage Facility

Adj Electricity Sub Station Strichen, Aberdeenshire, AB43 6RH

Electricity Sub Station, Strichen - Battery Storage Facility is a 50 MW battery storage project in Scotland. The applicant or operator on record is Intelligent Land Investments Group plc. Planning permission has been granted as of March 2022 and it is awaiting construction. The d…

Consented / Approved
Project stageConsented
  1. PlanningNov 2021 (completed)
  2. ConsentedMar 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2021-12-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Electricity Sub Station, Strichen - Battery Storage Facility is a 50 MW battery storage project in Scotland. The applicant or operator on record is Intelligent Land Investments Group plc. Planning permission has been granted as of March 2022 and it is awaiting construction. The determining authority is Aberdeenshire, reference APP/2021/2556.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperIntelligent Land Investments Group plc
Owner / operatorIntelligent Land Investments Group plc
Year consented2022
LocationAdj Electricity Sub Station Strichen, Aberdeenshire, AB43 6RH
RegionScotland
Coordinates57.5890688Β°N, 2.0649501Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-11-19
2022-03-01