Edge Lane, Maiden Law - Solar Farm & Battery Storage is a 45 MW battery storage project in North East. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of April 2026 and it is awaiting construction. The determining authority is County…

Consented / Approved
Project stageConsented
  1. PlanningJun 2022 (completed)
  2. ConsentedApr 2026 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Appeal Granted.

Official register: July 2026

Recorded status: Appeal Granted. Source record updated 2026-06-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

45.000 MW
Power Capacity

πŸ“‹ Project Overview

Edge Lane, Maiden Law - Solar Farm & Battery Storage is a 45 MW battery storage project in North East. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of April 2026 and it is awaiting construction. The determining authority is County Durham, reference DM/22/01769/FPA.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)45.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLightsource BP
Owner / operatorLightsource BP
Year consented2026
LocationEast Of Edge Lane Maiden Law, County Durham, DH7 0RY
RegionNorth East
Coordinates54.8349998Β°N, 1.7242209Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID11618

πŸ“… Project Timeline

2022-06-30
2026-04-22