North of Saline, Dunfermline, Fife, Fife, KY12 9UG
Easter Muirhead Farm is a 15 MW onshore wind project in Scotland. The applicant or operator on record is ABO Wind UK. The planning application was refused. The determining authority is Fife, reference 09/01359/WEIA.β¦
Refused
Project stageRefused
PlanningJun 2009 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2013-10-08.
Registered planning capacity; not measured generation.
Easter Muirhead Farm is a 15 MW onshore wind project in Scotland. The applicant or operator on record is ABO Wind UK. The planning application was refused. The determining authority is Fife, reference 09/01359/WEIA.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
15.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
ABO Wind UK
Owner / operator
ABO Wind UK
Location
North of Saline, Dunfermline, Fife, Fife, KY12 9UG