Solar Farm

East Yorkshire Solar Farm

Howden, Goole, East Riding of Yorkshire, DN14 7AE

East Yorkshire Solar Farm is a 400 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Boom Power. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authority is The Planning Inspectorate - Natio…

Consented / Approved
Project stageConsented
  1. PlanningNov 2023 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-07-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

400.000 MW
Registered Capacity

πŸ“‹ Project Overview

East Yorkshire Solar Farm is a 400 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Boom Power. Planning permission has been granted as of May 2025 and it is awaiting construction. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010143.

Site Schematic

SUBSTATION ? ha Β· 400 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)400.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBoom Power
Owner / operatorBoom Power
Year consented2025
LocationHowden, Goole, East Riding of Yorkshire, DN14 7AE
RegionYorkshire and Humber
Coordinates53.7469057Β°N, 0.8654485Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID15566
Mounting Type for SolarGround
Solar Site Area (sqm)12760000

πŸ“… Project Timeline

2023-11-21
2025-05-09