Clay Pit Hill Codford Down Eas, Codford, Warminster, Wiltshire, BA12 0PJ
East Codford Solar Farm Extension Phase 3 is a 18 MW solar farm project in South West. The applicant or operator on record is Centrica Plc. It is recorded as operational since September 2022. The determining authority is Wiltshire, reference 19/03576/FUL.β¦
OperationalΒ· Since 2022
Project stageOperating
PlanningApr 2019 (completed)
ConsentedDec 2020 (completed)
ConstructionApr 2022 (completed)
OperatingSep 2022 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2023-06-13.
Registered planning capacity; not measured generation.
East Codford Solar Farm Extension Phase 3 is a 18 MW solar farm project in South West. The applicant or operator on record is Centrica Plc. It is recorded as operational since September 2022. The determining authority is Wiltshire, reference 19/03576/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
18.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Centrica Plc
Owner / operator
Centrica Plc
Year consented
2020
Construction started
2022
Commissioned / target
2022
Location
Clay Pit Hill Codford Down Eas, Codford, Warminster, Wiltshire, BA12 0PJ