πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Dunsinane Industrial Estate

Land To The W/O Kinnoull Stree, Dunsinane Avenue, Dunsinane Industrial Estate, Dundee, Tayside, Tayside, DD2 3QT

Dunsinane Industrial Estate is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is JLEN Environmental Assets Group. It is recorded as operational since May 2023. The determining authority is Dundee City, reference 19/00876/FULL.…

Operational Β· Since 2023
Project stageOperating
  1. PlanningDec 2019 (completed)
  2. ConsentedFeb 2022 (completed)
  3. Construction (completed)
  4. OperatingMay 2023 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2023-05-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity
2023
Commissioned

πŸ“‹ Project Overview

Dunsinane Industrial Estate is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is JLEN Environmental Assets Group. It is recorded as operational since May 2023. The determining authority is Dundee City, reference 19/00876/FULL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperJLEN Environmental Assets Group
Owner / operatorJLEN Environmental Assets Group
Year consented2022
Commissioned / target2023
LocationLand To The W/O Kinnoull Stree, Dunsinane Avenue, Dunsinane Industrial Estate, Dundee, Tayside, Tayside, DD2 3QT
RegionScotland
Coordinates56.4803151Β°N, 3.0123553Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2019-12-02
2022-02-18
2023-05-03