Land To The W/O Kinnoull Stree, Dunsinane Avenue, Dunsinane Industrial Estate, Dundee, Tayside, Tayside, DD2 3QT
Dunsinane Industrial Estate is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is JLEN Environmental Assets Group. It is recorded as operational since May 2023. The determining authority is Dundee City, reference 19/00876/FULL.β¦
OperationalΒ· Since 2023
Project stageOperating
PlanningDec 2019 (completed)
ConsentedFeb 2022 (completed)
Construction (completed)
OperatingMay 2023 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2023-05-16.
Registered planning capacity; not measured generation.
Dunsinane Industrial Estate is a 49.9 MW battery storage project in Scotland. The applicant or operator on record is JLEN Environmental Assets Group. It is recorded as operational since May 2023. The determining authority is Dundee City, reference 19/00876/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
JLEN Environmental Assets Group
Owner / operator
JLEN Environmental Assets Group
Year consented
2022
Commissioned / target
2023
Location
Land To The W/O Kinnoull Stree, Dunsinane Avenue, Dunsinane Industrial Estate, Dundee, Tayside, Tayside, DD2 3QT