Dunkeswell Airfield

Dunkeswell Airfield, Dunkeswell Industrial Estate, Honiton, Devon, EX14 4LG

Dunkeswell Airfield is a 6.5 MW battery storage project in South West. The applicant or operator on record is Conrad (Tiddlywink) Limited. Planning permission has been granted as of November 2021 and it is awaiting construction. The determining authority is East Devon, reference …

Consented / Approved
Project stageConsented
  1. PlanningSep 2021 (completed)
  2. ConsentedNov 2021 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2021-11-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.500 MW
Power Capacity

πŸ“‹ Project Overview

Dunkeswell Airfield is a 6.5 MW battery storage project in South West. The applicant or operator on record is Conrad (Tiddlywink) Limited. Planning permission has been granted as of November 2021 and it is awaiting construction. The determining authority is East Devon, reference 21/2169/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.500 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperConrad (Tiddlywink) Limited
Owner / operatorConrad (Tiddlywink) Limited
Year consented2021
LocationDunkeswell Airfield, Dunkeswell Industrial Estate, Honiton, Devon, EX14 4LG
RegionSouth West
Coordinates50.8642626Β°N, 3.2273143Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-09-06
2021-11-23