πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Dulater Hill Wind Farm

North of the A923, near Butterstone, Highland

Dulater Hill Wind Farm is a 57.8 MW onshore wind project in Scotland. The applicant or operator on record is Ecotricity. The planning application was refused. The determining authority is Scottish Government (S36).…

Refused
Project stageRefused
  1. PlanningJun 2014 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Appeal Refused.

Official register: July 2026

Recorded status: Appeal Refused. Source record updated 2019-06-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

57.800 MW
Registered Capacity

πŸ“‹ Project Overview

Dulater Hill Wind Farm is a 57.8 MW onshore wind project in Scotland. The applicant or operator on record is Ecotricity. The planning application was refused. The determining authority is Scottish Government (S36).

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)57.800 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEcotricity
Owner / operatorEcotricity
LocationNorth of the A923, near Butterstone, Highland
RegionScotland
Coordinates56.6170072Β°N, 3.4854855Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)3.4
No. of Turbines17
Height of Turbines (m)125

πŸ“… Project Timeline

2014-06-30