Dudgeon East is a 402 MW offshore wind project in Offshore. The applicant or operator on record is Statoil / Statkraft. It is recorded as operational since October 2017. The determining authority is DECC (S36).…

Operational Β· Since 2017
Project stageOperating
  1. PlanningJun 2009 (completed)
  2. ConsentedJul 2012 (completed)
  3. ConstructionMar 2016 (completed)
  4. OperatingOct 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

402.000 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Dudgeon East is a 402 MW offshore wind project in Offshore. The applicant or operator on record is Statoil / Statkraft. It is recorded as operational since October 2017. The determining authority is DECC (S36).

Site Schematic

β—„ SHORE (~? km) NORTH SEA / OFFSHORE Turbine () Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)402.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatoil / Statkraft
Owner / operatorStatoil / Statkraft
Year consented2012
Construction started2016
Commissioned / target2017
LocationGreater wash, Offshore
RegionOffshore
Coordinates53.1174601Β°N, 0.6134682Β°E

Additional published register fields

Registered technologyWind Offshore
CfD Allocation RoundInvestment Contract
CfD Capacity (MW)402
Turbine Capacity (MW)6
No. of Turbines67

πŸ“… Project Timeline

2009-06-12
2012-07-06
2016-03-17
2017-10-15