Dryholme Farm (Farm AD)

Dryholme Farm, Silloth, Wigton,, Cumbria, CA7 4PZ

Dryholme Farm (Farm AD) is a 1 MW bioenergy / waste project in North West. The applicant or operator on record is Kirk Environmental. It is recorded as operational since November 2011. The determining authority is Cumberland, reference 2/2009/0864.…

Operational Β· Since 2011
Project stageOperating
  1. PlanningDec 2009 (completed)
  2. ConsentedJun 2010 (completed)
  3. ConstructionFeb 2011 (completed)
  4. OperatingNov 2011 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2011-12-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.000 MW
Registered Capacity
2011
Commissioned

πŸ“‹ Project Overview

Dryholme Farm (Farm AD) is a 1 MW bioenergy / waste project in North West. The applicant or operator on record is Kirk Environmental. It is recorded as operational since November 2011. The determining authority is Cumberland, reference 2/2009/0864.

πŸ”§ Technical Specifications

Capacity (MW)1.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKirk Environmental
Owner / operatorKirk Environmental
Year consented2010
Construction started2011
Commissioned / target2011
LocationDryholme Farm, Silloth, Wigton,, Cumbria, CA7 4PZ
RegionNorth West
Coordinates54.8562964Β°N, 3.3585717Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2009-12-02
2010-06-16
2011-02-01
2011-11-04