πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Drumcor Road

Lands 120m North East of, 14 Drumcor Road, Tempo, Enniskillen, Co Fermanagh, Co. Fermanagh, BT94 3FE

Drumcor Road is a 1 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. Planning permission has been granted as of July 2020 and it is awaiting construction. The determining authority is Fermanagh and Omagh, reference LA10/2019/1…

Consented / Approved
Project stageConsented
  1. PlanningOct 2019 (completed)
  2. ConsentedJul 2020 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2020-07-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.000 MW
Registered Capacity

πŸ“‹ Project Overview

Drumcor Road is a 1 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. Planning permission has been granted as of July 2020 and it is awaiting construction. The determining authority is Fermanagh and Omagh, reference LA10/2019/1228/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2020
LocationLands 120m North East of, 14 Drumcor Road, Tempo, Enniskillen, Co Fermanagh, Co. Fermanagh, BT94 3FE
RegionNorthern Ireland
Coordinates54.3846808Β°N, 7.4084603Β°W

Additional published register fields

Registered technologyWind Onshore
No. of Turbines1
Height of Turbines (m)67

πŸ“… Project Timeline

2019-10-17
2020-07-08