the Sandside Estate, Land 2215M SW Of Under Keepers, Sandside, Reay, Thurso, Highland, KW14 7RN
Drum Hollistan Wind Farm is a 51 MW onshore wind project in Scotland. The applicant or operator on record is Muirden Energy. The scheme is currently in the planning system, submitted October 2016. The determining authority is Scottish Government (S36), reference ECU00000243.β¦
Revised
Project stageSuperseded by a new application
PlanningOct 2016 (completed)
Superseded by a new application (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Revised.
Official register: July 2026
Recorded status: Revised. Source record updated 2019-06-25.
Registered planning capacity; not measured generation.
Drum Hollistan Wind Farm is a 51 MW onshore wind project in Scotland. The applicant or operator on record is Muirden Energy. The scheme is currently in the planning system, submitted October 2016. The determining authority is Scottish Government (S36), reference ECU00000243.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
51.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Muirden Energy
Owner / operator
Muirden Energy
Location
the Sandside Estate, Land 2215M SW Of Under Keepers, Sandside, Reay, Thurso, Highland, KW14 7RN