in the townlands of Douglas, Mistyburn, and Glenwhirry, Douglad Road, Ballymena, Co. Antrim, Co. Antrim
Douglas Top is a 51 MW onshore wind project in Northern Ireland. The applicant or operator on record is Macwindgen Limited. The application has been withdrawn or the scheme abandoned. The determining authority is Mid and East Antrim, reference G/2011/0182/F.β¦
Withdrawn
Project stageWithdrawn / abandoned
PlanningApr 2011 (completed)
Withdrawn / abandoned (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Application Withdrawn.
Official register: July 2026
Recorded status: Planning Application Withdrawn. Source record updated 2012-09-24.
Registered planning capacity; not measured generation.
Douglas Top is a 51 MW onshore wind project in Northern Ireland. The applicant or operator on record is Macwindgen Limited. The application has been withdrawn or the scheme abandoned. The determining authority is Mid and East Antrim, reference G/2011/0182/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
51.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Macwindgen Limited
Owner / operator
Macwindgen Limited
Location
in the townlands of Douglas, Mistyburn, and Glenwhirry, Douglad Road, Ballymena, Co. Antrim, Co. Antrim