Dorking Battery Energy Storage System is a 6 MW battery storage project in South East. The applicant or operator on record is Grid Battery Storage (GBSL). It is recorded as operational since July 2020. The determining authority is Mole Valley, reference MO/2016/1168.β¦
OperationalΒ· Since 2020
Project stageOperating
PlanningJul 2016 (completed)
Consented (completed)
ConstructionJan 2017 (completed)
OperatingJul 2020 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2020-07-31.
Registered planning capacity; not measured generation.
Dorking Battery Energy Storage System is a 6 MW battery storage project in South East. The applicant or operator on record is Grid Battery Storage (GBSL). It is recorded as operational since July 2020. The determining authority is Mole Valley, reference MO/2016/1168.