Donich Water Hydro is a 1.4 MW conventional hydro project in Scotland. The applicant or operator on record is Gilkes Energy/Broadland Energy. It is recorded as operational since September 2016. The determining authority is Argyll and Bute, reference 2013/0120/DET.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningMay 2013 (completed)
ConsentedSep 2014 (completed)
ConstructionOct 2015 (completed)
OperatingSep 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-10-26.
Registered planning capacity; not measured generation.
Donich Water Hydro is a 1.4 MW conventional hydro project in Scotland. The applicant or operator on record is Gilkes Energy/Broadland Energy. It is recorded as operational since September 2016. The determining authority is Argyll and Bute, reference 2013/0120/DET.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.