πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Offshore Wind

Dogger Bank A & B (was Creyke Beck A & B)

125km off coast of Yorkshire, Offshore

Dogger Bank A & B (was Creyke Beck A & B) is a 2,400 MW offshore wind project in Offshore. The applicant or operator on record is SSE/Equinor (formerly Statoil, formerly Forewind). It is recorded as under construction since July 2021. The determining authority is The Planning Ins…

Under Construction
Project stageUnder construction
  1. PlanningAug 2013 (completed)
  2. ConsentedFeb 2015 (completed)
  3. ConstructionJul 2021 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2022-04-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2,400.000 MW
Registered Capacity

πŸ“‹ Project Overview

Dogger Bank A & B (was Creyke Beck A & B) is a 2,400 MW offshore wind project in Offshore. The applicant or operator on record is SSE/Equinor (formerly Statoil, formerly Forewind). It is recorded as under construction since July 2021. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010021.

Site Schematic

β—„ SHORE (~? km) NORTH SEA / OFFSHORE Turbine () Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2,400.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSSE/Equinor (formerly Statoil, formerly Forewind)
Owner / operatorSSE/Equinor (formerly Statoil, formerly Forewind)
Year consented2015
Construction started2021
Location125km off coast of Yorkshire, Offshore
RegionOffshore
Coordinates55.9673366Β°N, 1.667921Β°E

Additional published register fields

Registered technologyWind Offshore
CfD Allocation RoundAR3
CfD Capacity (MW)2400
Turbine Capacity (MW)13
No. of Turbines190
Height of Turbines (m)260

πŸ“… Project Timeline

2013-08-29
2015-02-17
2021-07-01