Docks Way Disposal Site, Docks Way - Battery Energy Storage System

South Of Docks Way Disposal Site Docks Way, Gwent, NP20 2NS

Docks Way Disposal Site, Docks Way - Battery Energy Storage System is a 1 MW battery storage project in Wales. The applicant or operator on record is Newport City Council. Planning permission has been granted as of February 2026 and it is awaiting construction. The determining au…

Consented / Approved
Project stageConsented
  1. PlanningNov 2025 (completed)
  2. ConsentedFeb 2026 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-03-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.000 MW
Power Capacity

πŸ“‹ Project Overview

Docks Way Disposal Site, Docks Way - Battery Energy Storage System is a 1 MW battery storage project in Wales. The applicant or operator on record is Newport City Council. Planning permission has been granted as of February 2026 and it is awaiting construction. The determining authority is Newport, reference 25/0991.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNewport City Council
Owner / operatorNewport City Council
Year consented2026
LocationSouth Of Docks Way Disposal Site Docks Way, Gwent, NP20 2NS
RegionWales
Coordinates51.5708965Β°N, 3.000237Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-11-20
2026-02-12