Discovery Park is a 16 MW bioenergy / waste project in South East. The applicant or operator on record is Burmeister & Wain Scandinavian Contractor (BWSC). It is recorded as operational since September 2018. The determining authority is Dover, reference 13/00701.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningAug 2013 (completed)
  2. ConsentedOct 2013 (completed)
  3. ConstructionJun 2016 (completed)
  4. OperatingSep 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-09-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

16.000 MW
Registered Capacity
2018
Commissioned

πŸ“‹ Project Overview

Discovery Park is a 16 MW bioenergy / waste project in South East. The applicant or operator on record is Burmeister & Wain Scandinavian Contractor (BWSC). It is recorded as operational since September 2018. The determining authority is Dover, reference 13/00701.

πŸ”§ Technical Specifications

Capacity (MW)16.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBurmeister & Wain Scandinavian Contractor (BWSC)
Owner / operatorBurmeister & Wain Scandinavian Contractor (BWSC)
Year consented2013
Construction started2016
Commissioned / target2018
LocationRamsgate Road, Sandwich,, Kent, CT13 9ND
RegionSouth East
Coordinates51.2839088Β°N, 1.3456656Β°E

Additional published register fields

Registered technologyBiomass (dedicated)

πŸ“… Project Timeline

2013-08-23
2013-10-18
2016-06-23
2018-09-28