πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Other Registered Technology

Derwenthaugh Ecoparc

Derwenthaugh Ecoparc, Derwenthaugh Road, Swalwell, Newcastle-Upon-Tyne, Tyne and Wear, NE16 3BJ

Derwenthaugh Ecoparc is a 10 MW other registered technology project in North East. The applicant or operator on record is Graphite Resources. The scheme is currently in the planning system, submitted January 2014. The determining authority is Gateshead, reference DC/14/00034/FUL.…

Revised
Project stageSuperseded by a new application
  1. PlanningJan 2014 (completed)
  2. Superseded by a new application (project stopped here)
  3. ConsentedJul 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2015-10-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.000 MW
Registered Capacity

πŸ“‹ Project Overview

Derwenthaugh Ecoparc is a 10 MW other registered technology project in North East. The applicant or operator on record is Graphite Resources. The scheme is currently in the planning system, submitted January 2014. The determining authority is Gateshead, reference DC/14/00034/FUL.

πŸ”§ Technical Specifications

Capacity (MW)10.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGraphite Resources
Owner / operatorGraphite Resources
Year consented2014
LocationDerwenthaugh Ecoparc, Derwenthaugh Road, Swalwell, Newcastle-Upon-Tyne, Tyne and Wear, NE16 3BJ
RegionNorth East
Coordinates54.9636596Β°N, 1.6879972Β°W

Additional published register fields

Registered technologyAdvanced Conversion Technologies
Are they re-applying (New REPD Ref)5691

πŸ“… Project Timeline

2014-01-19
2014-07-22