Derehams Farm, Derehams Lane, Loudwater, High Wycombe, Buckinghamshire, HP10 9RR
Derehams Farm, Derehams Lane - Battery Storage is a 40 MW battery storage project in South East. The applicant or operator on record is Eku Energy / Statkraft. It is recorded as operational since August 2025. The determining authority is Buckinghamshire, reference 22/08045/FUL.β¦
OperationalΒ· Since 2025
Project stageOperating
PlanningNov 2022 (completed)
ConsentedJun 2023 (completed)
ConstructionFeb 2024 (completed)
OperatingAug 2025 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-02-13.
Registered planning capacity; not measured generation.
Derehams Farm, Derehams Lane - Battery Storage is a 40 MW battery storage project in South East. The applicant or operator on record is Eku Energy / Statkraft. It is recorded as operational since August 2025. The determining authority is Buckinghamshire, reference 22/08045/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
40.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Eku Energy / Statkraft
Owner / operator
Eku Energy / Statkraft
Year consented
2023
Construction started
2024
Commissioned / target
2025
Location
Derehams Farm, Derehams Lane, Loudwater, High Wycombe, Buckinghamshire, HP10 9RR