π Project Overview
Decoy Farm (Farm AD) is a 1.8 MW bioenergy / waste project in East Midlands. The applicant or operator on record is Organic Recycling. It is recorded as operational since July 2016. The determining authority is South Holland, reference H02-1061-10 & H02-0492-10.
π§ Technical Specifications
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Organic Recycling |
| Owner / operator | Organic Recycling |
| Year consented | 2011 |
| Construction started | 2015 |
| Commissioned / target | 2016 |
| Location | Spalding Road, Crowland, Peterborough, Lincolnshire, PE6 0LX |
| Region | East Midlands |
| Coordinates | 52.6968788Β°N, 0.1370658Β°W |
Additional published register fields
| Registered technology | Anaerobic Digestion |
|---|