Cyngor Sir Ynys Mon - Solar Photovoltaic Panels is a 0.49 MW solar farm project in Wales. The applicant or operator on record is Isle of Anglesey County Council. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is β¦
Consented / Approved
Project stageConsented
PlanningOct 2023 (completed)
ConsentedJan 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-01-23.
Registered planning capacity; not measured generation.
Cyngor Sir Ynys Mon - Solar Photovoltaic Panels is a 0.49 MW solar farm project in Wales. The applicant or operator on record is Isle of Anglesey County Council. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is Isle of Anglesey, reference FPL/2023/232.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.490 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Isle of Anglesey County Council
Owner / operator
Isle of Anglesey County Council
Year consented
2024