Cupar Wastewater Treatment Works Solar Farm is a 0.62 MW solar farm project in Scotland. The applicant or operator on record is Scottish Water (Dundee). It is recorded as operational since July 2021. The determining authority is Fife, reference 20/02141/FULL.…

Operational Β· Since 2021
Project stageOperating
  1. PlanningOct 2020 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingJul 2021 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2021-11-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.620 MW
Registered Capacity
2021
Commissioned

πŸ“‹ Project Overview

Cupar Wastewater Treatment Works Solar Farm is a 0.62 MW solar farm project in Scotland. The applicant or operator on record is Scottish Water (Dundee). It is recorded as operational since July 2021. The determining authority is Fife, reference 20/02141/FULL.

Site Schematic

SUBSTATION ? ha Β· 0.62 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.620 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottish Water (Dundee)
Owner / operatorScottish Water (Dundee)
Year consented2021
Commissioned / target2021
LocationCupar W W T W, Fife, KY15 4SX
RegionScotland
Coordinates56.3225757Β°N, 2.9918934Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround & Roof
Solar Site Area (sqm)1368

πŸ“… Project Timeline

2020-10-23
2021-01-19
2021-07-19