πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Culmhead Business Park - Ground Mounted Photovoltaic Solar Array

Western Provident Association, Culmhead Business Park, Taunton, Somerset, TA3 7DY

Culmhead Business Park - Ground Mounted Photovoltaic Solar Array is a solar farm project in South West. The applicant or operator on record is Western Provident Association. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining a…

Consented / Approved
Project stageConsented
  1. PlanningDec 2023 (completed)
  2. ConsentedJan 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-01-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Culmhead Business Park - Ground Mounted Photovoltaic Solar Array is a solar farm project in South West. The applicant or operator on record is Western Provident Association. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is Somerset, reference 10/23/0023.

Site Schematic

SUBSTATION ? ha Β· MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWestern Provident Association
Owner / operatorWestern Provident Association
Year consented2024
LocationWestern Provident Association, Culmhead Business Park, Taunton, Somerset, TA3 7DY
RegionSouth West
Coordinates50.9293932Β°N, 3.1269719Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)6700

πŸ“… Project Timeline

2023-12-04
2024-01-10