Culham Science Centre, Clifton Hampden - Battery Storage Facility

N/O Culham Science Centre, Near Clifton Hampden, Abingdon, Oxfordshire, OX14 3ES

Culham Science Centre, Clifton Hampden - Battery Storage Facility is a 500 MW battery storage project in South East. The applicant or operator on record is Statera Energy. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining author…

Consented / Approved
Project stageConsented
  1. PlanningMay 2024 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Appeal Granted.

Official register: July 2026

Recorded status: Appeal Granted. Source record updated 2025-08-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

500.000 MW
Power Capacity

πŸ“‹ Project Overview

Culham Science Centre, Clifton Hampden - Battery Storage Facility is a 500 MW battery storage project in South East. The applicant or operator on record is Statera Energy. Planning permission has been granted as of July 2025 and it is awaiting construction. The determining authority is South Oxfordshire, reference P24/S1498/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)500.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatera Energy
Owner / operatorStatera Energy
Year consented2025
LocationN/O Culham Science Centre, Near Clifton Hampden, Abingdon, Oxfordshire, OX14 3ES
RegionSouth East
Coordinates51.6633565Β°N, 1.2307143Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-05-09